Roadmap — mission plan

Four phases, measurable exit criteria. A milestone only turns green when a build-log entry declares it reached — with evidence.

  1. Phase 0 — bench test

    wk 1–3 · upcoming

    • in progressOrder everything up front
    • upcomingEach sensor validated individually
    • upcomingFive streams readable simultaneously
  2. Phase 1 — Correlator on the bench

    wk 3–6 · upcoming

    • upcomingFan / drill / magnet-on-a-pole protocol
    • upcomingThree scenarios classified correctly 9 times out of 10 — blocking milestone
  3. Phase 2 — fit and finish

    wk 6–9 · upcoming

    • upcomingTactical Night interface working
    • upcomingVideo black box operational
    • upcomingThree-stage A.R.V.A. v2
    • upcoming3D-printed enclosure assembled, haptics wired
    • upcomingClean magnetic-noise test before final assembly
  4. Phase 3 — field

    wk 9+ · upcoming

    • upcomingFirst mission in an uncontrolled location
    • upcomingFalse positives per hour measured
    • upcomingReal battery life measured

Open doors

Explorations. Nothing built, nothing promised.


Risk register

Published as is. The first three dominate.

#RiskProb.ImpactMitigation
1Scope creephighhighPhase 1 milestone (9/10) is blocking; new ideas → open doors
2Residual self-interferencemediumhighClean-noise test before assembly; longer snout; local mu-metal; Silence mode
3Field false positiveshighmediumFP/h metric; black-box diagnosis → iterative refinement
4Software complexitymediummedium1 sensor = 1 process; central event bus
5Volatile supplymediummediumOrder everything in phase 0; spares; RTL-SDR V3 (stable production)
6Heat in a closed enclosuremediummedium15 W mode by default; ventilation; throttling watch in phase 2
7Sentinel privacylowhighAnonymized fingerprints only, never raw addresses; AES-256 encrypted logs
8A.R.V.A. disappointmentmediumlowAccepted and documented: quality and traceability over quantity